S&P warns of "downgrading" data centers, aiming to "add fuel" to the AI debt crisis.

华尔街见闻10-24 10:20

S&P GlobalThe ratings warned that the data center industry is facing the risk of a credit rating downgrade, triggered by a wave of local government bans and public opposition sweeping across the United States.

According to a Bloomberg report on October 24, S&P Global Ratings pointed out in a report released on Friday (October 23) that project delays caused by grid capacity constraints, environmental sustainability controversies, and zoning adjustments..."This may increase downward pressure on the credit quality of data center projects."。 S&P tracked 146 delayed or canceled data center projects in the United States, about three-quarters of which were directly related to local opposition.

S&P also pointed out thatIf a ban, slowdown in permit approval, or policy reversal results in substantial project delays, financial penalties such as rent reductions or even the tenant's right to terminate the contract will constitute a real credit risk.。 Although the actual impact on credit ratings is still limited, this warning undoubtedly casts a shadow over the data center industry, which is currently in a period of rapid expansion.

Local bans spread to 40 states and 146 projects were blocked

The data center construction boom has sparked widespread public scrutiny in recent months. According to a S&P report, local governments in 40 states across the United States have successively introduced bans or restrictions.

S&P's analysis focuses on bans in five states: New York, Texas, Pennsylvania, Illinois, and Arizona, and tracks bans across the United States.146 data center projects delayed or cancelledAbout three-quarters of this stemmed from opposition at the local level.

Objections frequently cited by local communities include:Rising energy costs, water scarcity, air pollution, and noise pollution。

Financial penalties and the right to terminate contracts, credit risk has already taken shape.

S&P's report clearly outlines the transmission paths of credit risk.If a project cannot proceed on schedule due to injunctions or approval delays, developers may face financial penalties for paying rent reductions to tenants, and in severe cases, tenants may even exercise their right to terminate the contract.

The report points out that the aforementioned risks "constitute credit hazards in the form of financial penalties such as rent reductions and exemptions, and even the right of tenants to terminate."

S&P also acknowledged that the actual impact of the ban on credit ratings so far has been "limited," but the wording carries a clear warning sense—The combined pressures of power grid capacity constraints, environmental disputes, and zoning changes are systematically increasing project credit risk.。

This S&P report reveals structural obstacles to the expansion of the data center industry.On the demand side, AI infrastructure construction continues to drive a surge in data center investment; But on the supply side,Power grid capacity bottleneck, stricter environmental supervision and local community resistanceMultiple constraints are emerging.

S&P's analysis indicates that this contradiction has evolved from a public opinion level into a quantifiable credit risk factor. For investors holding data center-related debt, local policy trends and project progress will become variables that cannot be ignored in assessing credit quality.

Disclaimer: Investing carries risk. This is not financial advice. The above content should not be regarded as an offer, recommendation, or solicitation on acquiring or disposing of any financial products, any associated discussions, comments, or posts by author or other users should not be considered as such either. It is solely for general information purpose only, which does not consider your own investment objectives, financial situations or needs. TTM assumes no responsibility or warranty for the accuracy and completeness of the information, investors should do their own research and may seek professional advice before investing.